September 10, 2022
Hon. Frank Tayali announces that the President intends to commission the Bridge in Kanchibiya
August 19, 2022
Delays are due to unforeseen challenges faced by the engineering contractor
August 04, 2022
TAZARA Board approves Budget for 2022/2023, adjusts passenger fares and resolves to form Technical Committee to chart way for revamping operations as directed by the Heads of State
July 13, 2022
The completion of repairs has been delayed due to late arrival of steel parts for the bridge
June 10, 2022
Muchinga Province Permanent Secretary visits site to check on progress
June 09, 2022
Passenger train services between Tanzania and Zambia will resume after 22 July 2022
April 28, 2022
Contractor gives assurances that work progress on the damaged bridge was on course.
February 25, 2022
Hopkas Engineering Conultants Ltd of Lusaka has been mandated to provide supervisory services of the repair  of the Chambeshi Railway Bridge on behalf of TAZARA.
February 24, 2022
Railway operations across the Chambeshi Bridge now expected to resume in July 2022, following the signing of a Contract to repair the Bridge. Passenger trains will also resume border crossings in July.